Understanding Access Requests

An access request moves from the catalog, through the approval stages of its configuration's policy, to provisioning on the target, and, for time-limited access, to removal when it ends. This page explains each part and how they fit together.

How it works

  1. A configuration publishes the access. An active request configuration puts an application, its entitlements, a privileged asset, its groups or shared accounts, or a new identity in the end-user Access Catalog. Its Requestors rules decide who sees it.
  2. Someone submits a request. The person picks the access, a duration if offered, and a justification if the policy requires one. If the configuration allows it, they can request for someone else.
  3. Zetect builds the approval stages. The configuration's approval policy decides the stages. Each stage's approver is worked out at this moment, for example the requester's line manager. A configuration with no policy is approved automatically.
  4. Approvers decide, stage by stage. Only the current stage's clock runs. Approvers see the request's risk and any segregation-of-duties conflict before they decide. A rejection at any stage ends the request.
  5. Zetect provisions the access. When the last stage approves, Zetect sends the provisioning action, such as create account or add to group. If the access never reaches the target, the request becomes Failed until you retry it.
  6. Time-limited access ends. When the access expiry passes, Zetect removes the access, unless the person still holds it another way.

Approval stages

A policy approves in one of three ways: Automatically, By one approver, or In several stages. Each stage has:

  • An approver. Application Owner, Line Manager, a Named User or a Security Team (Group). If a stage's approver can't be worked out, for example a requester with no manager, the stage goes to the resource owner.
  • A step duration. How long the stage may wait, in hours or days. With No limit, it waits until someone decides. A stage's clock starts when the previous stage is approved.
  • A timeout action. What happens when the step duration runs out: Escalate, Move to next stage, Auto-reject or Auto-approve. With no action set, the request moves to the next stage, or is rejected at the last stage.
  • A group decision, for group approvers. With Any one member, the first member to decide closes the stage. With All members, every member must approve, and one rejection decides.

Requests already in progress keep the stage settings they started with, even if you edit the policy later.

No self-approval

Nobody approves their own request. If a stage's approver would be the requester, or the person who submitted it for them, the stage goes to the requester's line manager or, failing that, to the resource owner. If neither exists, the stage's timeout action decides it straight away: Auto-approve approves the stage, Auto-reject rejects the request, and anything else passes it to the next stage, or rejects it at the last stage. A group approver the requester belongs to stays in place, but the requester can't vote in it.

Risk and conflicts at approval time

Approvers see Risk if granted: the provisioning risk level the access would add, with the signals that contribute to it. If the access would conflict with a segregation-of-duties policy, the approver sees each conflict. Approving still grants the access: the conflict is recorded as a violation for the policy owner, and risk is flagged in the audit log. Neither stops provisioning. See Configuring Provisioning Risk and Preventing Policy Violations.

Requests for others

A configuration can let chosen people, such as managers or a service desk, request for someone else. The person who receives the access is the requester of record: provisioning, their access list, certifications, SoD and risk all treat the request as theirs, and they must still meet the configuration's Requestors rules. Neither they nor the person who submitted the request can approve it. See Enabling Requests for Others.

Request grants and automatic provisioning

Access granted through an approved request is kept when Zetect re-checks a person against provisioning policies and Who can access rules. It ends only when it expires, is revoked in a certification or SoD remediation, is given up, or the person is deactivated. See How Provisioning Works.

Example

RequestDaniel Okafor asks for FIN-Reports in Finance ERP for 90 days
PolicyManager then Security: Line Manager (2 days → Move to next stage), then Security Team (Group) SecOps (All members, 3 days → Escalate)
Stage 1His manager approves on day 1. Stage 2's clock starts.
Stage 2Both SecOps members approve on day 3.
FulfilmentZetect sends Add to Group. Outcome: "Added to the group", access ends in 90 days.
Day 93The access expires and Zetect removes it. Outcome: "Access removed when it ended".

Limits and defaults

  • Step duration: up to 365 days, or no limit.
  • An escalated stage is reassigned once, with a fresh step duration. If that also lapses, the request moves on, or is rejected at the last stage.
  • Move to next stage is not allowed on the last stage.
  • A multi-stage policy with no stages approves automatically.
  • Shared-account access is always time-limited. Default choices are 1 h, 4 h, 8 h and 1 d, with a maximum of 7 days.
  • Requests for others are not available for New Identity configurations.
  • Roles can't be requested as a whole yet.